Agriculture Ministry Building
Agriculture Ministry Building

The Need:

Grid-tie: its apart of Egyptian government plan to improve the national grid
with alternative and green power sources.
Emergency and backup: ministry building is very important and critical load
and depending on diesel generators as backup isn’t very reliable compared to
solar power.

Solution :

1- based on load profile of 20KW emergency system was installed which consists
of :
component configuration
Solar PV 10 KW(luxor)
Solar chargers 10 KW (STUDER)(2 X variostring)
inverter 21 KW (STUDER) (3X xtender XTH-8000)
Battery 72 cells (2V 8RES OPzS  1275 AH)
2-based on load profile of 20KW emergency system was installed which consists
of :
component configuration
Solar PV 10 KW(luxor)
Solar chargers 10 KW (STUDER) (2 X variostring)
inverter 21 KW (STUDER ) (3X xtender XTH-8000)
Battery 72 cells (2V 8RES OPzS  1275 AH)
3-Grid-tie system of 120 KW:
component configuration
Solar PV 120 KW (luxor)
inverter 100 KW (REFUsol) (5x20KW) .

 

 


OVERVIEW

Pv solar power plant 140 Kw Roof mounted. project consists of : 1-120 kw pv panel connected to grid-tie. inverter 2-20 kW pv panel connected to backup and emergency system for ministry building.


THE RESULT

140 Kw solar power plant feed the ministry building and give backup system for important and critical Loads . Project status : finished and working .