Naser City District Building
Naser City District Building

The Need:

Grid-tie: its apart of Egyptian government plan to improve the national grid
with alternative and green power sources.
Solution :

Grid-tie system of 60 KW:
component configuration
Solar PV 60 KW (luxor)
inverter 20 KW( Advanced Energy )(3x20KW ) .

 


OVERVIEW

 Pv solar power plant 60 Kw Roof mounted. project consists of : 60 kw pv panel connected to grid-tie inverter .


THE RESULT

60 Kw solar power plant feeds  the district building . Project status : finished and working .