The Need:

 

its a part of Egyptian Government plan to improve distant roads and supply them with electric power.

 

Solution :

1- Based on load profile of  50 KW emergency system was installed which consists of:

component  configuration
Solar PV : 135 KW (Luxor)
Hybrid inverter : INGECONR SUN STORAGE Power  80 Kw
String Inverter : 112 KW(ingeteam)( 4 X ingecon 3play-TL 28 Kw )
Battery: 330 cells (2V 11 RES OPzS 2285 AH)

 


OVERVIEW

off –Grid solar project to supply 372 LED luminaire with electricity for 12 hours . Pv solar power plant 50 Kw Free Field . project consists of : 135 kw pv panel connected to off Grid system. Project status : finished and working .


THE RESULT

50 Kw solar power plant feeds 372 Led Luminaire with electricity for 12 Hours / daily .